PROJECT OVERVIEW | ||
Programme: | CBC SRB-BiH 2014-2020 | |
Call for Proposals: | 1st | |
Application No: | 52 | |
Contract No. | 48-00-00046/2016-28-8 signed on July 19th, 2019 | |
Project Title: | Improving Solid Waste Management in Urban and Rural Areas of Bajina Bašta, Višegrad and Han Pijesak municipalities | |
Specific objective: | SO 2.1: Improving sustainable environmental planning and promotion of biodiversity | |
Result: | R 1: The effectiveness of public services and practices in relation to solid waste and wastewater management are enhanced through joint initiatives at both sides of the border | |
Project budget: | Total contract amount (€): | Contracted amount EU (€) and
% of total contract amount: |
€ 735,574.56 | € 625,238.38
85% |
|
Beneficiaries of funds: | Lead applicant: | Co-applicants: |
Public Utility Company “12 Septembar” Bajina Bašta | BiH
· Public Utility Company “Komunalac” A.D. Višegrad · Public Utility Company “Kraljeva Gora” DOO, Han Pijesak” |
|
Location of the action: | SRB: | BiH: |
Western Serbia, Zlatibor Region, Bajina Basta Municipality | Bosnia and Herzegovina, Republic of Srpska, Visegrad and Han Pijesak Municipality | |
Target groups: | • 1.000 inhabitants of three municipalities
• 70 employees in three municipalities • 360 (pre)school age children • 80 educators for further knowledge transfer • 20 media representatives |
|
Commencement date and project duration: | July 20th, 2019, 27 months | |
Overall objective: | Contribution to the promotion of sustainable environmental planning in the cross-border area of Serbia-Bosnia and Herzegovina. | |
Specific objective(s) or project purpose: | Improved efficiency of public services in the field of waste management by establishing a system of separate collection and treatment of municipal waste in the entire territory of the municipalities of Bajina Basta, Visegrad and Han Pijesak. | |
Activities and results of the project
|
RESULT NO. 1: Technical preconditions for integrated municipal WM established on the territory of three municipalities
Activity no. 1.1: Procurement/distribution of specialized WM equipment Activity no. 1.2: Development and introduction of primary waste collection system in the rural areas of BB Activity no.1.3: Development and introduction of a primary waste collection system on the entire territory of two municipalities of B&H Activity no.1.4: Establishment of a pilot compost plant in BB RESULT NO. 2 : The process of continuous education of key stakeholders in the integrated municipal WM process established in three municipalities Activity no. 2.1: Implementation of continuous education of the population of three municipalities Activity no. 2.2 Realization of a study trip RESULT NO. 3: Municipal planning documents in the field of WM developed/applied in three municipalities Activity no. 3.1: Preparation of project planning documentation for the municipal compost plant in BB Activity no. 3.2: Development/adoption of six legal development documents RESULT NO. 4: Local community familiar with the results of the action Activity no. 4.1: Production/distribution of promo materials Activity no. 4.2: Development/implementation of media campaigns Activity no. 4.3: Organisation of Project kick-off and final conferences |
|